Array ( [id] => 403103 [appid] => 1 [topicid] => 0 [galleryid] => 0 [channel_pc] => 1 [channel_wap] => 1 [channel_phone] => 1 [channel_pad] => 0 [title] => 新集水电站:全力冲刺并网发电 [editor] => 李春辉 [has_thumb] => 1 [created] => 2022-12-05 19:14:22 [published] => 2022-12-05 19:14:22 [modified] => 2022-12-06 10:52:41 [digg] => 0 [pv] => 0 [comments] => 0 [shares] => 2 [recommend] => 0 [importance] => 0 [status] => 6 [enablecopyright] => 0 [sort] => 0 [origin] => 0 [syscomments] => 0 [main_category] => 976 [flow_step] => 0 [flow_id] => 0 [flow_index] => [gzh_account_id] => 0 [gzh_account_name] => [short_title] => [content] =>

12月5日,施工人员在新集水电站现场抓紧施工。

目前是水电站施工的最佳时期,近千名工人在项目鏖战,为了做好疫情防控和项目建设两不误,新集水电站组织现场6家主要施工单位成立“萤火虫志愿服务队”,轮班24小时值守,保障施工安全,确保项目顺利推进。

新集水电站工程是汉江干流九级开发中的第四级,具有通航、发电和灌溉的作用,目前正处于最后的冲刺阶段。襄阳新集水电站技术负责人朱辉说:“现在现场全天不间断施工,全力以赴冲刺明年5月首台机组并网发电的目标。”

记者:谢勇;通讯员:张沛;

审核:安富斌;编辑:李春辉;

终审:刘志国;校对:张文进;

运营:襄阳日报社


[subtitle] => [pagecount] => 1 [sourceurl] => [banner] => Array ( ) [description] => [thumb] => Array ( [url] => https://img.cjyun.org.cn/a/10125/202212/7255515c338dd3851eccc71d5b4cafc6.jpg [id] => 2777952 ) [url] => http://xiangyang.cjyun.org/p/403103.html [wapurl] => http://m-xiangyang.cjyun.org/p/403103.html [attachments] => Array ( ) [relates] => Array ( ) [gallery] => Array ( ) [galleries] => Array ( ) [menu] => 0 [authors] => 记者:谢勇;通讯员:张沛; [author] => 记者:谢勇;通讯员:张沛; [terms] => Array ( [4] => Array ( [0] => 襄阳日报 ) [2] => Array ( [0] => 新集水电站 ) [1] => ) [thumbs] => Array ( [0] => Array ( [url] => https://img.cjyun.org.cn/a/10125/202212/7255515c338dd3851eccc71d5b4cafc6.jpg [id] => 2777952 ) ) [all_pv] => 0 ) 1

新集水电站:全力冲刺并网发电

2022-12-05 19:14   襄阳日报  

12月5日,施工人员在新集水电站现场抓紧施工。

目前是水电站施工的最佳时期,近千名工人在项目鏖战,为了做好疫情防控和项目建设两不误,新集水电站组织现场6家主要施工单位成立“萤火虫志愿服务队”,轮班24小时值守,保障施工安全,确保项目顺利推进。

新集水电站工程是汉江干流九级开发中的第四级,具有通航、发电和灌溉的作用,目前正处于最后的冲刺阶段。襄阳新集水电站技术负责人朱辉说:“现在现场全天不间断施工,全力以赴冲刺明年5月首台机组并网发电的目标。”

记者:谢勇;通讯员:张沛;

审核:安富斌;编辑:李春辉;

终审:刘志国;校对:张文进;

运营:襄阳日报社


0 条评论
来说两句吧。。。
最新
来说两句吧...