Array ( [id] => 164970 [appid] => 1 [topicid] => 0 [galleryid] => 0 [channel_pc] => 1 [channel_wap] => 1 [channel_phone] => 1 [channel_pad] => 0 [title] => 鄂北水资源配置工程计划明年年底全线通水 [editor] => 姚喻 [has_thumb] => 1 [created] => 2018-06-10 17:17:58 [published] => 2018-06-10 17:17:58 [modified] => 2018-06-10 21:59:34 [digg] => 1 [pv] => 0 [comments] => 0 [shares] => 0 [recommend] => 0 [importance] => 0 [status] => 6 [enablecopyright] => 0 [sort] => 0 [origin] => 0 [syscomments] => 0 [main_category] => 0 [flow_step] => 0 [flow_id] => 0 [flow_index] => [gzh_account_id] => 0 [gzh_account_name] => [short_title] => [content] =>

  鄂北调水工程是从根本上解决鄂北地区干旱缺水问题的重大战略民生工程。记者从水利部门了解到,目前工程建设正有序推进,主通道预计明年6月底通水,明年年底前可实现全线通水。

  记者来到襄州区古驿镇宋湾村,在鄂北水资源配置工程第6标段的白河管线桥施工现场看到,这里的工人们正忙着引桥段的T梁建设及主桥段的连续梁施工。

  白河管线桥总长636.4米,跨河的管桥在白河右侧与岗地相接。考虑到河面较宽及后期通航需要,主桥采用单箱三室的连续箱梁,并采用悬臂浇筑法进行施工。建成后桥面宽度将达19. 8米,可容纳直径为3.8米的三根管并列放置。

  鄂北调水工程襄州段全长52.16公里,通过3排深埋式PCCP管涵输水,共设计了黑清河水库、官沟水库、夹河套、千亩大堰、樊庄水库等5个分水口,预计明年6月份完工。工程建设完成后可使襄州区的10个镇及东津新区受益,可解决47万亩耕地灌溉及25万人农村居民饮水问题,为东津新区40万城区市民提供应急保障。

  在老河口,鄂北调水工程建设也在提速。目前3.85公里的暗涵、1.26公里的明渠土方已经完工,全长0.24公里的倒虹吸建设也在稳步推进中。

  孟楼渡槽是丹江口渠首以下第一座大型输水渡槽工程,里程长、架设难度大。施工人员采用“槽上运槽”的办法加快进度,目前槽身安装已经完成了3.7公里,完成了安装总量的80%,预计整个孟楼渡槽工程在2018年12月底可以全部完成如期安装施工。

  鄂北调水工程2014年开工以来,我市提出“最大力度服务支持工程建设,最大限度实现工程受益目标”。老河口、襄州、枣阳三地及12个沿线乡镇各自组建工作专班,集中办公,专职做好对接、协调、推进工作。眼下,26个标段正加紧施工,滕庄、樊庄、高庵、管沟等4个分水口已开始进行配套工程建设。预计今年年底完工。

  据市水利局局长陈启合介绍,(鄂北调水)这个项目的实施,将使襄阳218万人、224万亩农田从中受益,项目实施竣工以后,会极大地改善襄阳北部地区长期干旱的问题,整个主通道按照省里计划,有望明年6月底通水,整个主通道所有段在明年年底前全线通水。

记者:刘春梅 / 编辑:姚喻 / 校对:王晓

责编:曾雄飞 / 审核:曾雄飞

[subtitle] => [pagecount] => 1 [sourceurl] => [banner] => Array ( ) [description] => 鄂北水资源配置工程计划明年年底全线通水 [thumb] => Array ( [url] => https://img.cjyun.org.cn/a/10125/201806/3212bfb977d34e731c94c393efcfbbea.png [id] => 1193814 ) [url] => http://xiangyang.cjyun.org/p/164970.html [wapurl] => http://m-xiangyang.cjyun.org/p/164970.html [attachments] => Array ( ) [relates] => Array ( ) [gallery] => Array ( ) [galleries] => Array ( ) [menu] => 0 [authors] => [author] => [terms] => Array ( [2] => Array ( [0] => 襄州 [1] => 鄂北 [2] => 调水 [3] => 渡槽 ) [4] => Array ( [0] => 襄阳广播电视台 襄州台 老河口台 ) [1] => ) [thumbs] => Array ( [0] => Array ( [url] => https://img.cjyun.org.cn/a/10125/201806/3212bfb977d34e731c94c393efcfbbea.png [id] => 1193814 ) ) [oldpv] => 498 [all_pv] => 0 ) 1

鄂北水资源配置工程计划明年年底全线通水

2018-06-10 17:17   襄阳广播电视台 襄州台 老河口台  

  鄂北调水工程是从根本上解决鄂北地区干旱缺水问题的重大战略民生工程。记者从水利部门了解到,目前工程建设正有序推进,主通道预计明年6月底通水,明年年底前可实现全线通水。

  记者来到襄州区古驿镇宋湾村,在鄂北水资源配置工程第6标段的白河管线桥施工现场看到,这里的工人们正忙着引桥段的T梁建设及主桥段的连续梁施工。

  白河管线桥总长636.4米,跨河的管桥在白河右侧与岗地相接。考虑到河面较宽及后期通航需要,主桥采用单箱三室的连续箱梁,并采用悬臂浇筑法进行施工。建成后桥面宽度将达19. 8米,可容纳直径为3.8米的三根管并列放置。

  鄂北调水工程襄州段全长52.16公里,通过3排深埋式PCCP管涵输水,共设计了黑清河水库、官沟水库、夹河套、千亩大堰、樊庄水库等5个分水口,预计明年6月份完工。工程建设完成后可使襄州区的10个镇及东津新区受益,可解决47万亩耕地灌溉及25万人农村居民饮水问题,为东津新区40万城区市民提供应急保障。

  在老河口,鄂北调水工程建设也在提速。目前3.85公里的暗涵、1.26公里的明渠土方已经完工,全长0.24公里的倒虹吸建设也在稳步推进中。

  孟楼渡槽是丹江口渠首以下第一座大型输水渡槽工程,里程长、架设难度大。施工人员采用“槽上运槽”的办法加快进度,目前槽身安装已经完成了3.7公里,完成了安装总量的80%,预计整个孟楼渡槽工程在2018年12月底可以全部完成如期安装施工。

  鄂北调水工程2014年开工以来,我市提出“最大力度服务支持工程建设,最大限度实现工程受益目标”。老河口、襄州、枣阳三地及12个沿线乡镇各自组建工作专班,集中办公,专职做好对接、协调、推进工作。眼下,26个标段正加紧施工,滕庄、樊庄、高庵、管沟等4个分水口已开始进行配套工程建设。预计今年年底完工。

  据市水利局局长陈启合介绍,(鄂北调水)这个项目的实施,将使襄阳218万人、224万亩农田从中受益,项目实施竣工以后,会极大地改善襄阳北部地区长期干旱的问题,整个主通道按照省里计划,有望明年6月底通水,整个主通道所有段在明年年底前全线通水。

记者:刘春梅 / 编辑:姚喻 / 校对:王晓

责编:曾雄飞 / 审核:曾雄飞

0 条评论
来说两句吧。。。
最新
来说两句吧...